Scope of the contract: Detailed design, construction supervision, and assistance with commissioning and testing for the revamping of the BMS (Building Management System) serving the HVAC systems of a public building in downtown Lecco.
Project Objective: To modernize the control systems using a state-of-the-art, open, and remotely accessible monitoring system, while retaining the existing terminal wiring and ensuring that office operations continue uninterrupted.
Key Information
Client Name: Lombardy-based HVAC installation company
Project Name: Revamping the BMS system of a public building in downtown Lecco
Project period: May 2026 – ongoing (plant in operation and undergoing testing since August 2026)
Buildings involved: Public building used for offices, training rooms, and a civic hall, in downtown Lecco
Brief description of the planned activities
System Adjustments and Issues with the Existing System
The building was controlled by older-generation PLCs in the central control panels and AHU control panels, while the fan coil units were controlled by older-generation KNX controllers, with room units connected via a dedicated bus.
A fragmented system that is difficult to manage and lacks true centralized oversight.
Systems involved: heating plant, chiller, three air-handling units, radiant panels, 54 fan coil units
The solution: Revamp the brain, preserve the infrastructure
The key design decision was to retain the existing KNX infrastructure of the terminals. Before beginning the design phase, we thoroughly analyzed the network: 180 devices and over 500 group addresses, which were reconstructed and optimized. Based on this, the new system reuses existing cables and backbones, offering three immediate advantages:
• no rewiring of terminal units and a quick installation process;
• Minimal disruption for occupants, with offices remaining fully operational;
• Controlled costs, focused on value-generating components.
The heating plant, three AHUs, and the chiller system were upgraded to four new BACnet/IP controllers on the Niagara platform, connected to the existing Ethernet network. The chiller was integrated via remote I/O, without modifying its onboard controller.
Fan Coil Unit Control and Management of the Nine Zones
In each room, the old thermostat has been replaced with a new KNX room thermostat (44 in total), featuring a display and local setpoint adjustment, while the 54 fan coil units are controlled by new dedicated controllers.
The new controller integrates the summer/winter switching function, eliminating 39 KNX binary outputs that served only this purpose: fewer devices, fewer points of failure, and lighter bus lines.
The building is divided into nine zones, each with its own schedule of operating modes (comfort, standby, economy).
The building setpoints are managed centrally by the supervisory system, and thanks to hot and cold start-up, the fan starts only when the battery has reached the desired temperature, without introducing cold air in winter or warm air in summer.
BMS System Monitoring and Remote Access via VPN
The supervisor, based on the Niagara framework, runs on a virtual machine within the client’sIT infrastructure and can be accessed via a browser and remotely via VPN, without the need for dedicated workstations. It communicates with the controllers over the IP network and reads the KNX bus directly via KNX/IP, without a protocol conversion gateway: a streamlined architecture based on open protocols and free from vendor lock-in.
Operating Facilities Based on Actual Demand
The chiller unit, boilers, and distribution pumps start up only when there is an actual demand from the loads, as indicated by the status of the control valves.
All systems are controlled and monitored by the BMS (Building Management System):
- heating plant with three boilers in cascade and twin inverter-controlled pumps,
- refrigeration unit,
- air handling unit,
- radiant panels,
- fan coil units.
The result is a system that consumes energy only when necessary and can be monitored in its entirety.
From Design to Testing of the BMS System
In the executive project we defined in great detail the architecture of the BMS system , the regulation logic and the integration between the systems , delivering to the system integrator a project ready for programming and commissioning .
We then accompanied the construction site in the works management and supported the integrator in the commissioning .
During commissioning, the entire checklist was verified item by item, and all control logic was tested in the field.
Finally, all project documentation was updated to reflect the as-built status to facilitate the operation, maintenance, and future expansion of the plant.
Upgrading BMS Systems in Existing Buildings
This project is a concrete example of how a well-designed BMS system upgrade can provide an existing building with a modern management system, making the most of what’s already there.
Enertech Solution supports the client from the designto the construction management, through toassistance with the commissioning and testing of the BMS system.
Would you like to upgrade the control and monitoring of your systems? Contact our team or explore our other projects in the Projectssection.